Construction
Preliminary – Initial Planning
- Perimeter Flags, corner posts located – complete
- Address Sign Posted – complete
- Site Walk, Corners Staked – complete
- Survey – complete
- Preliminary Site Plans, determine area for soil test, general layout – current
- Soil Test to determine the percolation rate of soil for septic placement. Determine native soil or sand leach field.
- Create Engineered/refined Site Plans
Phase 1 Scope Overview
Phase 1 includes:
• Site clearing and grading
• Compacted native soil driveway and building pad
• Frost-Protected Shallow Foundation (radiant-ready slab)
• Well drilling and septic system (sized for future expansion)
• Engineered yurt structure installation
• Snow- and wind-rated enclosure
• Solar power system and electrical distribution
• Plumbing and HVAC systems
• Interior buildout to move-in readiness
The result:
A code-compliant, fully operational dwelling designed for durability and long-term stability.
Typical Construction Timeline
~ 6 Months from Mobilization to Move-In Readiness
(Weather, inspection, and material lead times dependent)
Month 1 – Site Preparation
Permitting, utility layout, grading, well and septic coordination.
Milestone: Site prepared for foundation.
Month 2 – Foundation & Infrastructure
Radiant slab installation, well drilling, septic system placement.
Milestone: Cured slab with operational utilities.
Month 3 – Structure & Enclosure
Yurt erection, doors/windows, weather-tight completion.
Milestone: Fully enclosed structure.
Month 4 – Mechanical Systems
Electrical, plumbing, HVAC installation and inspections.
Milestone: Functional core systems.
Month 5 – Interior Completion
Partitions, finishes, fixtures, appliances.
Milestone: Move-in ready.
Month 6 – Finalization
Inspections, punch list, driveway finish, site cleanup.
Milestone: Occupancy-ready.